3rd of December 2013. Site clean in preparation for the R9 panel tracks to be laid on the slab. The wall panels slot into metal tracks around the perimeter of the slab.

Site Clean

Site clean rear view
23RD of December 2013. The track system that the R9 panels slot into has started to be put in place on the slab. After this everything slows down after Christmas for a few weeks.

R9 panel track

Tracks down ready for panels
20TH of January 2014. Ready to unload the panels from the truck but a minor setback of the forklift getting bogged holds us up for a day. Oops.

Forklift setback
21ST January 2014. The panels have been unloaded and the first panels are up! all in the same day. I have never seen a build this quick, the crew are fantastic, seriously hardworking blokes. Our house has it’s first walls, happy days.

Panels unloaded and first panels up

First panels up day 1
22ND January 2014. By the end of the second day there are more walls to the lower floor.

Second day progress

Second day wall progress

Second day progress rear view

Second day progress inside view Great Room

external wall office and laundry

Day 3 progress